Aerial view of the siteWinner of three
industry awards, embankment stabilisation works for Thrandeston Bog
designed by Mott MacDonald represent the first use of an innovative
ground treatment technique - dry soil mixing - to stabilise a key
part of the UK rail network. The works mark a UK first in terms of
the application of dry soil mixing immediately adjacent to a live
railway for the treatment of up to 10m of peat and very soft clay
whilst maintaining the full use of the railway. The project was
delivered to a cost of some 50% less than the client’s original
scheme, saving more than £6 million, and achieved a more
environmentally sustainable solution with a lower carbon footprint
for the site, located in a rural and environmentally sensitive part
of Suffolk.
Site conditions at Thrandeston, located on the strategically
important London to Norwich mainline, have historically proved
problematic, dating back to the construction of the original Great
Eastern Railway in 1847. Constrained by the ground conditions at
the site, comprising over 10m of peat and very soft clays, the
original construction was subject to repeated slope failure and
excessive embankment settlement.
More than 150 years on, the challenges at Thrandeston Bog continued
for Network Rail. Instability of the embankment, some 650m in
length and up to 5m high was ongoing with movement of the both the
tracks and overhead power line stanchions. The asset required a
high degree of maintenance and monitoring while the possibility of
embankment failure would threaten the continued operation of this
mainline railway.
In 2006 Network Rail employed Mott MacDonald to provide a detailed
design for the stabilisation of the railway embankment, increasing
the design life of the structure for a further 120 years. There was
also a desire to provide a solution aesthetically sympathetic to
the rural setting of the site that could be implemented without
adversely affecting a wet meadow Site of Special Scientific
Interest located along the boundary of the site.
Dry soil mixing rig in operation adjacent to live
railway tracksMott MacDonald proposed the use of dry
soil mixing to realise the project aims, strengthening the peat and
soft clay upon which the railway embankment was founded and
effectively creating stabilised ground either side of the railway
tracks. The technology was applied immediately adjacent to a live
railway, up to 2.75m from the existing overhead electrified line,
establishing a UK first. This design solution was proposed and
accepted by Network Rail in preference to a conventional piling
scheme consisting of a line of tubular steel piles installed along
both sides of the embankment.
From inception of the dry soil mixing scheme Mott MacDonald
provided a suite of services to Network Rail, including preliminary
and detailed design, production of specifications, advice on
contacts and selection of a preferred contactor and technical
support during construction encompassing both the ground
engineering works and environmental support. Additionally, Mott
MacDonald designed new gantry structures as a replacement for the
existing overhead line stanchions and designed a new culvert that
was installed beneath the embankment adopting a guided auger-bored
installation technique.
Technique and scheme design
Dry soil mixing is used for increasing the strength of very soft
soils. The technique injects and then mixes cement powder into the
soil to create columns of stronger material, known as soilcrete.
The scheme design involved installation of approximately 11,000
soil mix columns (total meterage 75,000) in panels along both sides
of the embankment. The ground treatment effectively buttressed the
soft ground beneath the railway lines to prevent it from spreading
laterally and the track level setting. Application of the scheme
required the following research and studies:
- numerical modelling to validate the long term performance of
the treated ground using as a basis the European Soil Stabilisation
research findings; and
- laboratory and field studies to demonstrate the effectiveness
of the treated ground at the site prior to implementation and for
value engineering the design in the field.
Research, laboratory and field studies
The application of the dry soil mixing technique, using the
EuroSoilStab project as a basis established the principles for work
at Thrandeston Bog. This research was extended by Mott MacDonald to
encompass the particular site specific constrains of implementing
the works immediately adjacent to a live railway, with particular
focus on the long term embankment settlement and the application of
recent research on the lateral spreading of soft clays.
Finite element numerical modelling was undertaken, which utilised a
non-linear stress-strain-time dependant model to represent the
behaviour of the peat and very soft clays which demonstrated that
the long term track movements over the lifetime of the earth
structure would not exceed tolerable limits.
The second element of the design development entailed extensive
laboratory and field studies to demonstrate that the soil mixing
would significantly improve the strength of the soft ground and to
optimise the cement dosage required to achieve the design
strengths. To accomplish these goals a programme of field and
laboratory testing in excess of £100,000 was implemented.
Innovation and value
Technical innovation achieved reductions to both
cost and environmental impactsInitially the results of
the laboratory tests were disappointing as the strength of the soil
mix materials were relatively low. However, subsequent field
studies demonstrated the suitability of dry soil mixing technique
and identified further value engineering opportunities through the
use differing cement contents for the treatment of the clay and
peat zones along the length of the site. This led to significant
savings of around £100,000.
The application of the dry soil mixing in favour of a conventional
piled solution also created a more environmentally sustainable
solution with manufacture of the raw material generating 80% less
embodied energy at a cost of less than half of the pile solution,
saving the scheme more than £6 million – demonstrating the clear
advantages of the dry soil mixing solution.
The project’s accomplishments demonstrate Mott MacDonald’s
commitment to delivering innovative solutions, illustrating the
value of investing in developing technologies and undertaking
applied research. Industry recognition of the project has followed
since completion, with the project succeeding in winning three
awards.
The completed embankmentThe project
triumphed at the 2009 ACE Engineering Excellence Awards, claiming
the prize for Research, Studies and Consulting, while the Ground
Engineering Awards saw the scheme take the top award for Project
with a Geotechnical Value over £1 million where it was also highly
commended in the Innovation Award category. At the Institution of
Civil Engineers, East of England Merit Awards the project succeeded
in winning in the Innovation and Technical Excellence Award
category and the project was also Highly Commended in the National
Rail Awards, Civil Engineering Achievement of the Year award
category.