Skip navigation

Home About us Capability Markets Projects Careers Contact us
 
Search




Browse


A3 Hindhead Improvements A34 Chieveley/M4 Junction 13 Improvement A38 Glynn Valley Slope Stabilisation Althorp Embankment Boston CA-T Instrumentation Boston Central Artery Cork Docklands Crossing Cork Harbour and Shannon Estuary cable alignment studies Delhi Metro Dubai Soil Mapping Guyana Sea Defences Heathrow ART Hunstanton Cliff Assessment Incheon Bridge Karachaganak Processing Complex M25 Flint Hall Farm Morfa to Berwick Link Road N14/N13 Junction Overstrand Cliff Stability Penarth Marina Escarpment Sirte Port Development Tannur Dam Victoria Station Upgrade Western Isles Coastal Protection Western Isles coastal protection project appraisal
 

Heathrow ART

BAA’s £140 million Airside Road Tunnel (ART) was developed as an improvement to facilities at London’s Heathrow Airport. It facilitates the transfer of passengers and baggage between the central terminal area and aircraft stands located on the western edge of the airport serving the newly opened Terminal 5.

Ramp during construction
The ART consists of two bored tunnels each 1.3km long and 8.1m internal diameter with a further 500m of ramp at each end built as cut-and-cover structures. The scheme also includes nine emergency escape cross passages between the two tunnels, two 20m long tunnels for electrical equipment and two sump facilities built inside the tunnels. These structures have been constructed using an innovative one-pass shotcrete lining.

Mott MacDonald Role


TBM cutterhead
Mott MacDonald was a key member of the integrated team appointed by BAA to help deliver the ART. Working with contractors AMEC, Laing O’Rourke Civil Engineering and Morgan-Vinci JV, our role covered responsibility for initial planning and feasibility along with preliminary and detailed design of all works. This included the definition of the tunnel alignment, approval of tunnel construction methodology to ensure integrity of the tunnel face, management of the geotechnical investigation, design of the segmental tunnel lining and design of the tunnel ventilation system and tunnel services.

Project Highlights


ART bored tunnelThe project demanded extensive excavation up to 17m deep for the tunnel portals beneath busy taxiways and aircraft stands while passing above the existing Piccadilly Line tunnel. Keeping the rail tunnels operational and minimising disruption above ground were also key requirements throughout construction. The contractual framework set up by BAA encouraged innovation and allowed value enhancing alternatives to be designed and implemented for the tunnel portals. Here, together with BAA and Laing O’Rourke, we developed an Observational Method scheme which eliminated the need for temporary steel propping and overcame severe spatial and logistical constraints.

West portal TBM chamberThe need to minimise ground settlement caused by excavation through London Clay at shallow depth below aircraft taxiways, stands and fuel lines led to use of an earth pressure balance tunneling machine (EPBM) with the additional provision of compressed air as an alternative method of supporting the tunnel face. Mott MacDonald experts carried out the prediction of settlement movements from the tunnel excavation. To ensure trains could continue to run in the Piccadilly Line and Heathrow Express tunnels while the construction was carried out nearby, a real time electronic monitoring scheme was used, its supply and installation procured from a specialist subcontractor to manage the monitoring throughout construction.

We also undertook a site surveillance role of the tunnel and civil engineering works to ensure quality, with specific responsibility for the minimizing the impact on third parties.



© Mott MacDonald Group Limited 2008
Site by Mott MacDonald and Radley Yeldar ›