A3 Hindhead Improvements A34 Chieveley/M4 Junction 13 Improvement A38 Glynn Valley Slope Stabilisation Althorp Embankment Boston CA-T Instrumentation Boston Central Artery Cork Docklands Crossing Cork Harbour and Shannon Estuary cable alignment studies Delhi Metro Dubai Soil Mapping Guyana Sea Defences Heathrow ART Hunstanton Cliff Assessment Incheon Bridge Karachaganak Processing Complex M25 Flint Hall Farm Morfa to Berwick Link Road N14/N13 Junction Overstrand Cliff Stability Penarth Marina Escarpment Portsmouth Harbour coastal revetments Siadar Breakwater EIA Sirte Port Development Tannur Dam Victoria Station Upgrade Western Isles Coastal Protection Western Isles coastal protection project appraisal
Related links

Geotechnical asset management
Read about our role

Remedial earthworks design
Read about this specialist discipline

See our work in
Slope management and vegetation

Applied geomorphology
Read abour our assessment techniques

 

Althorp Embankment

Deformed rail trackDeformation of track associated with failure mechanismMott MacDonald was appointed by Birse Rail to undertake a ground investigation and design remedial works to mitigate the risk associated with the vegetation and stabilise the embankment.

Ground investigation and inclinometer monitoring results indicated a progressive failure mechanism was occurring within the highly plastic Lias Clay embankment materials leading to track movement. The mechanisms were modelled in the finite element software PLAXIS to assess the factor of safety and associated improvements gained through implementation of remedial works.


Soil nailingSoil nail installation to stabilise embankmentRemedial works design was undertaken to Network Rail standards with the production of Form A Approval in Principle and Form B documentation.

Permanent works comprised an innovative double row of soil nailed gabions with earthworks fill to stabilise the progressive failure mechanism and provide additional cess support. Inclinometer monitoring was undertaken over a 12 month period to confirm movements had ceased.