Skip navigation

Home About us Capability Markets Projects Careers Contact us
 
Search




Browse


A3 Hindhead Improvements A34 Chieveley/M4 Junction 13 Improvement A38 Glynn Valley Slope Stabilisation Althorp Embankment Boston CA-T Instrumentation Boston Central Artery Cork Docklands Crossing Cork Harbour and Shannon Estuary cable alignment studies Delhi Metro Dubai Soil Mapping Guyana Sea Defences Heathrow ART Hunstanton Cliff Assessment Incheon Bridge Karachaganak Processing Complex M25 Flint Hall Farm Morfa to Berwick Link Road N14/N13 Junction Overstrand Cliff Stability Penarth Marina Escarpment Portsmouth Harbour coastal revetments Siadar Breakwater EIA Sirte Port Development Tannur Dam Victoria Station Upgrade Western Isles Coastal Protection Western Isles coastal protection project appraisal
 

A34 Chieveley/M4 Junction 13 Improvement

Junction aerial viewM4 Junction 13 showing the underpass for the A34 and the new sliproadsWorking with design and build contractor Costain Civil Engineering Mott MacDonald was appointed as designer for the A34 Chieveley improvement scheme – developed to alleviate major congestion and so improve safety at the interchange of the M4 and A34 Junction 13.

Geotechnical design was required for ten bridges, retaining walls, earthworks, pavement and drainage.

The landmark structure carries the M4 (with two slip roads) over the new A34 dual carriageway. The bridges were constructed on large diameter contiguous bored piles with top down sequencing to maintain three lanes of live traffic, each way, at all times on the M4. Six of the other bridges have bored piled foundations while the other structure has contiguous bored pile retaining wall abutments.

Solution feature in bored pile wall, earthworks were designed and constructed with a split slope profile due to the presence of an interface between soil and chalk typically occurring within the main cutting. A reinforced soil bund was also constructed to provide environmental screening for several houses adjacent to the road.

In order to minimise the amount of material imported to the site, stabilised capping was constructed using lime and cement or cement only. In addition, maximum re-use was made of site won road planning in pavement layers to further reduce the requirement to import material.

Underpass constructionUnderpass during constructionThe presence of solution features (randomly distributed pockets of weak soil) was an ever present risk to construction. The presence of unexpected features had the potential to impact on all elements of the scheme with potentially serious effects, particularly for the main underpass structure. This was managed by a full time site engineering geologist who used field observations and a ‘toolkit’ of pre-designed solutions to mitigate risks for each element of construction.


© Mott MacDonald Group Limited 2008
Site by Mott MacDonald and Radley Yeldar ›